Oracle Primavera - PM6 Member for 19 years 3 months Member for 19 years 4 months Submitted by Ijaz Ahmad on Wed, 2007-06-06 16:35 Permalink RE: Calculating Duration of Summary Tasks Thanks Andrew Member for 20 years 11 months Member for 20 years 11 months Submitted by Andrew Podolny on Wed, 2007-06-06 15:06 Permalink RE: Calculating Duration of Summary Tasks The duration of summary task are calculated based on Default calendar. To change it go to Enterprise-->Calendars... and change the Default calendar by checking the box. Regards, Andrew Log in or register to post comments
Member for 19 years 3 months Member for 19 years 4 months Submitted by Ijaz Ahmad on Wed, 2007-06-06 16:35 Permalink RE: Calculating Duration of Summary Tasks Thanks Andrew
Member for 20 years 11 months Member for 20 years 11 months Submitted by Andrew Podolny on Wed, 2007-06-06 15:06 Permalink RE: Calculating Duration of Summary Tasks The duration of summary task are calculated based on Default calendar. To change it go to Enterprise-->Calendars... and change the Default calendar by checking the box. Regards, Andrew
Member for
19 years 3 monthsRE: Calculating Duration of Summary Tasks
Thanks Andrew
Member for
20 years 11 monthsRE: Calculating Duration of Summary Tasks
The duration of summary task are calculated based on Default calendar. To change it go to Enterprise-->Calendars... and
change the Default calendar by checking the box.
Regards,
Andrew