Calendar by défault and specific calendar

Member for

22 years 8 months

Another point may help.



If you link two activity together, by default, the link will base on the predecessor calendar, however, you can change it by changing the schedule option to use to successor calendar.



Alex

Member for

20 years 11 months

Yes indeed all summary WBS durations are based on default calendar. However you can create your own task under the WBS you want to be calculated by different calendar and set it to WBS Summary activity type then assign the Calendar you like. No predecessors/successors needed.

Cheers

Andrew

Member for

19 years

Patricia,



Sorry, I don’t quite get your query. Can you explain it more details so I can absorb the problem.



Note:

WBS summary inherit the duration from the WBS element or any activities/ task under your WBS summary. What ever calendar you used for those activities under WBS summary the start and finish date should be the earliest start of the task and latest early finish date of the task.



Regards,

Rodel

Member for

20 years 6 months

I generally don’t rely on the values indicated in the WBS summary groups for anything other than start and finish dates, as some rather interesting results are shown for Float/%/duration..

Member for

18 years 5 months

Rodel,



OK to change of calendar at Project lavel.



But, my troubles are in the fact there could be, in ine single project one specific calendar for one or a few WBS elements, and the default calendar for the other ones. In that case, the calculated Remaining Duration at WBS element level is wrong if you compare with the remaining duration of the activities.



Regards.

Patricia

Member for

19 years

Patricia,



You can use and define as many calendars you want in a project but you need to assign it in to your activities. All those activities without any calendar assign it will use the default calendar. You can assign a default calendar in a project module.



Select Enterprise-> Projects then select the default tab and select a calendar to use as default in calendar box.



Hope this help.



Rodel