If you link two activity together, by default, the link will base on the predecessor calendar, however, you can change it by changing the schedule option to use to successor calendar.
Alex
Member for
20 years 11 months
Member for20 years11 months
Submitted by Andrew Podolny on Wed, 2007-06-06 16:27
Yes indeed all summary WBS durations are based on default calendar. However you can create your own task under the WBS you want to be calculated by different calendar and set it to WBS Summary activity type then assign the Calendar you like. No predecessors/successors needed.
Cheers
Andrew
Member for
19 years
Member for19 years
Submitted by Rodel Marasigan on Wed, 2007-06-06 04:43
Sorry, I dont quite get your query. Can you explain it more details so I can absorb the problem.
Note:
WBS summary inherit the duration from the WBS element or any activities/ task under your WBS summary. What ever calendar you used for those activities under WBS summary the start and finish date should be the earliest start of the task and latest early finish date of the task.
Regards,
Rodel
Member for
20 years 6 months
Member for20 years7 months
Submitted by Santosh Bhat on Wed, 2007-06-06 03:20
I generally dont rely on the values indicated in the WBS summary groups for anything other than start and finish dates, as some rather interesting results are shown for Float/%/duration..
Member for
18 years 5 months
Member for18 years5 months
Submitted by Patricia Le Clainche on Wed, 2007-06-06 02:34
But, my troubles are in the fact there could be, in ine single project one specific calendar for one or a few WBS elements, and the default calendar for the other ones. In that case, the calculated Remaining Duration at WBS element level is wrong if you compare with the remaining duration of the activities.
Regards.
Patricia
Member for
19 years
Member for19 years
Submitted by Rodel Marasigan on Wed, 2007-06-06 01:55
You can use and define as many calendars you want in a project but you need to assign it in to your activities. All those activities without any calendar assign it will use the default calendar. You can assign a default calendar in a project module.
Select Enterprise-> Projects then select the default tab and select a calendar to use as default in calendar box.
Member for
22 years 8 monthsRE: Calendar by défault and specific calendar
Another point may help.
If you link two activity together, by default, the link will base on the predecessor calendar, however, you can change it by changing the schedule option to use to successor calendar.
Alex
Member for
20 years 11 monthsRE: Calendar by défault and specific calendar
Yes indeed all summary WBS durations are based on default calendar. However you can create your own task under the WBS you want to be calculated by different calendar and set it to WBS Summary activity type then assign the Calendar you like. No predecessors/successors needed.
Cheers
Andrew
Member for
19 yearsRE: Calendar by défault and specific calendar
Patricia,
Sorry, I dont quite get your query. Can you explain it more details so I can absorb the problem.
Note:
WBS summary inherit the duration from the WBS element or any activities/ task under your WBS summary. What ever calendar you used for those activities under WBS summary the start and finish date should be the earliest start of the task and latest early finish date of the task.
Regards,
Rodel
Member for
20 years 6 monthsRE: Calendar by défault and specific calendar
I generally dont rely on the values indicated in the WBS summary groups for anything other than start and finish dates, as some rather interesting results are shown for Float/%/duration..
Member for
18 years 5 monthsRE: Calendar by défault and specific calendar
Rodel,
OK to change of calendar at Project lavel.
But, my troubles are in the fact there could be, in ine single project one specific calendar for one or a few WBS elements, and the default calendar for the other ones. In that case, the calculated Remaining Duration at WBS element level is wrong if you compare with the remaining duration of the activities.
Regards.
Patricia
Member for
19 yearsRE: Calendar by défault and specific calendar
Patricia,
You can use and define as many calendars you want in a project but you need to assign it in to your activities. All those activities without any calendar assign it will use the default calendar. You can assign a default calendar in a project module.
Select Enterprise-> Projects then select the default tab and select a calendar to use as default in calendar box.
Hope this help.
Rodel