Baseline 2 in P3e

Member for

18 years 7 months

Thanks Raviraj.

I have an other question



After assigning resource budgeted and actual units . In resource usage profile graph, it shows budgeted , remaining unit curves but not "actual units curve". if we double click on graph it will give all values of budgeted, remaining as well as actuals . I also click on "resource usage profile options" .



Thanks

Minhas

Member for

18 years 5 months

Copy the baseline 1 project and then change the data date you required.



Remove all actual start and actual finish dates. This can be easily done through global change.



Now make the necessary changes you require.



Hope this is clear.



Cheers,



Raviraj A Bhedase