Oracle Primavera - PM6 Member for 20 years Member for 20 years Submitted by Marcio Sampaio on Fri, 2007-07-27 20:22 Permalink RE: Project Managemnet- Primaver 5.0 Chek Primavera windows divider. Member for 18 years 5 months Member for 18 years 5 months Submitted by raed hussein on Fri, 2007-06-01 07:20 Permalink RE: Project Managemnet- Primaver 5.0 thank you mr/ james skelton you solve my problem Member for 20 years 5 months Member for 20 years 6 months Submitted by James Skelton on Thu, 2007-05-31 11:49 Permalink RE: Project Managemnet- Primaver 5.0 check you timescale start & timescale finish in page setup option tab. I have found that if the timescale is not set for your projects approximate start & finish then the gantt will not show Member for 19 years 11 months Member for 19 years 11 months Submitted by niles luo on Wed, 2007-05-30 22:14 Permalink RE: Project Managemnet- Primaver 5.0 Maybe you forget to click the Gantt Chart button. Member for 18 years 5 months Member for 18 years 5 months Submitted by raed hussein on Wed, 2007-05-30 08:41 Permalink RE: Project Managemnet- Primaver 5.0 only table is shown Member for 23 years Member for 23 years Submitted by Steven Oliver on Wed, 2007-05-30 07:44 Permalink RE: Project Managemnet- Primaver 5.0 What is shown ? Log in or register to post comments
Member for 20 years Member for 20 years Submitted by Marcio Sampaio on Fri, 2007-07-27 20:22 Permalink RE: Project Managemnet- Primaver 5.0 Chek Primavera windows divider.
Member for 18 years 5 months Member for 18 years 5 months Submitted by raed hussein on Fri, 2007-06-01 07:20 Permalink RE: Project Managemnet- Primaver 5.0 thank you mr/ james skelton you solve my problem
Member for 20 years 5 months Member for 20 years 6 months Submitted by James Skelton on Thu, 2007-05-31 11:49 Permalink RE: Project Managemnet- Primaver 5.0 check you timescale start & timescale finish in page setup option tab. I have found that if the timescale is not set for your projects approximate start & finish then the gantt will not show
Member for 19 years 11 months Member for 19 years 11 months Submitted by niles luo on Wed, 2007-05-30 22:14 Permalink RE: Project Managemnet- Primaver 5.0 Maybe you forget to click the Gantt Chart button.
Member for 18 years 5 months Member for 18 years 5 months Submitted by raed hussein on Wed, 2007-05-30 08:41 Permalink RE: Project Managemnet- Primaver 5.0 only table is shown
Member for 23 years Member for 23 years Submitted by Steven Oliver on Wed, 2007-05-30 07:44 Permalink RE: Project Managemnet- Primaver 5.0 What is shown ?
Member for
20 yearsRE: Project Managemnet- Primaver 5.0
Chek Primavera windows divider.
Member for
18 years 5 monthsRE: Project Managemnet- Primaver 5.0
thank you mr/ james skelton you solve my problem
Member for
20 years 5 monthsRE: Project Managemnet- Primaver 5.0
check you timescale start & timescale finish in page setup option tab. I have found that if the timescale is not set for your projects approximate start & finish then the gantt will not show
Member for
19 years 11 monthsRE: Project Managemnet- Primaver 5.0
Maybe you forget to click the Gantt Chart button.
Member for
18 years 5 monthsRE: Project Managemnet- Primaver 5.0
only table is shown
Member for
23 yearsRE: Project Managemnet- Primaver 5.0
What is shown ?