the way I help clients chose which duration type to use is to tell them that each activity has THREE dimensions:
Duration
Number of men
Total Manhours (duration x Number of men)
If you ask an engineer how "big" a job is, do they tell you:
Its a three day job
Its a two man job
Its a 50 manhour job
By ranking the above list, and comparing it to the order that each of those variables is recalculated by the four duration types, you should be able to work out which is best.
I am blessed with clients who scope the work for Shutdowns/Turnarounds very well. So in that world its a "50 manhour job" - so we use "Fixed duration and units"
Member for
20 years
Member for20 years
Submitted by Marcio Sampaio on Fri, 2007-07-27 20:20
Member for
21 yearsRE: P5 for shutdown planning
All,
the way I help clients chose which duration type to use is to tell them that each activity has THREE dimensions:
Duration
Number of men
Total Manhours (duration x Number of men)
If you ask an engineer how "big" a job is, do they tell you:
Its a three day job
Its a two man job
Its a 50 manhour job
By ranking the above list, and comparing it to the order that each of those variables is recalculated by the four duration types, you should be able to work out which is best.
I am blessed with clients who scope the work for Shutdowns/Turnarounds very well. So in that world its a "50 manhour job" - so we use "Fixed duration and units"
Member for
20 yearsRE: P5 for shutdown planning
I used same during a HOT STRIP MILL Repair.
Regards.
Member for
18 years 9 monthsRE: P5 for shutdown planning
Hi Alka
We used it for shutdown planning.
Fixed duration and units seems the best choice.
You plan with fixed durations --> no surprises with the overall duration
Fixed Units: better for the planned resource load and by this for simulations.
Good luck
Dieter