updating the baseline??need help

Member for

18 years 5 months

Hi amit,



If you dont have baseline program saved, then copy the updated project and then do the following



Go to Global Change and put



If AS Is Greater Than "Baseline date"

Then

AS = " "

AF = " "

PCT = = o



This will definitely help you



Somebody has given this post before, please check the previous links. You may get some good stuff.



Cheers,



Raviraj

Member for

18 years 6 months

Hi Amit,



I want to understand, dont you have a baseline schedule in place? Which is usually the case, we have a baseline and we have the live updated schedule.



If the answer is no then you can copy the live project and make a baseline (target). It will be bit of manual work to modify the updated project rsources and dates etc. Let us know the specific places where you face problem modifying the baeline manually.





Regards,





Ashraf