If they are still there and you can’t work out why.



As I’ve just found out, if you have no requirement for Logic links to external projects, add the columns ’External Early Start’ & ’External Late Finish’, then remove any data in there.



This will then clear the remainder of the "*".



Andy

Member for

18 years 6 months

Thanks for your help

Member for

19 years

mh shaw,



On the activity detail select the status tab and remove any constrains and date shown on the constrains box



Hope this help.



Rodel