Deb is correct. I forgot to mention that you need to set the decimal on duration format. Edit-> Users Preferences... under your project menu.
Select Time Unit Tab and change the duration format to 1 or 2 decimal. If this is not set the calculation still based on 7.5 hours but shown as 8hrs round off. You will notice only on the total durations.
Regards,
Rodel
Member for
18 years 9 months
Member for18 years9 months
Submitted by Pranab Kumar Deb on Mon, 2007-04-30 01:54
I had already done that, but I suppose my question is more because when I assign a resource to a 1 day activity, it assigns that resource with 8hrs of work and budget - even though the calendar for that resource is also set as default 7.5hr/day.. I can override this and type in 7.5 in the units column, which gives the right budget, but it still displays 8 (because of rounding?) in the units column.. Is there a way to correct this and show the decimal place in the units field?..
Thanks again!
Beck
Member for
19 years
Member for19 years
Submitted by Rodel Marasigan on Mon, 2007-04-30 01:31
Member for
19 yearsRE: 7.5hr working day?
Beck,
Deb is correct. I forgot to mention that you need to set the decimal on duration format. Edit-> Users Preferences... under your project menu.
Select Time Unit Tab and change the duration format to 1 or 2 decimal. If this is not set the calculation still based on 7.5 hours but shown as 8hrs round off. You will notice only on the total durations.
Regards,
Rodel
Member for
18 years 9 monthsRE: 7.5hr working day?
u have to change in project over view to 2 decimal places , i hope this will solve the rounding problem
regards
deb
Member for
18 years 10 monthsRE: 7.5hr working day?
Thanks for your reply Rodel..
I had already done that, but I suppose my question is more because when I assign a resource to a 1 day activity, it assigns that resource with 8hrs of work and budget - even though the calendar for that resource is also set as default 7.5hr/day.. I can override this and type in 7.5 in the units column, which gives the right budget, but it still displays 8 (because of rounding?) in the units column.. Is there a way to correct this and show the decimal place in the units field?..
Thanks again!
Beck
Member for
19 yearsRE: 7.5hr working day?
Hi Beck,
Yes you can set the calendar for 7.5hrs default for a work day.
First Create a global calendar with 7.5 hrs working day. Then click this calendar or set as default.
Regards,
Rodel