Be very careful when using a Mandatory constraint as it ignores all network logic.



KB

Member for

19 years

Hi Rodrigo,



Using Mandatory Finish as your constrain will remove your total float even you have float originally before constraining your activity. If you used mandatory finish dated earlier than schedule then you will have a negative float. This required changing your logic to override your negative float and change it back to 0 float.