Oracle Primavera - PM6 Member for 19 years 7 months Member for 19 years 7 months Submitted by Karim Mounir on Sun, 2007-04-15 01:04 Permalink RE: Summarization % of Base Line for P5 Hi Omar, Checkout this post: http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=30849 it may helps. Regards, Karim Member for 18 years 6 months Member for 18 years 7 months Submitted by Omar A.S. on Thu, 2007-04-12 00:53 Permalink RE: Summarization % of Base Line for P5 Dear IC Quiamco Yes I mean Unit% & Duration % and another things BL Remaining Duration in Summary Thanks Omar A.S Log in or register to post comments
Member for 19 years 7 months Member for 19 years 7 months Submitted by Karim Mounir on Sun, 2007-04-15 01:04 Permalink RE: Summarization % of Base Line for P5 Hi Omar, Checkout this post: http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=30849 it may helps. Regards, Karim
Member for 18 years 6 months Member for 18 years 7 months Submitted by Omar A.S. on Thu, 2007-04-12 00:53 Permalink RE: Summarization % of Base Line for P5 Dear IC Quiamco Yes I mean Unit% & Duration % and another things BL Remaining Duration in Summary Thanks Omar A.S
Member for
19 years 7 monthsRE: Summarization % of Base Line for P5
Hi Omar,
Checkout this post:
http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=30849
it may helps.
Regards,
Karim
Member for
18 years 6 monthsRE: Summarization % of Base Line for P5
Dear IC Quiamco
Yes I mean Unit% & Duration % and another things BL Remaining Duration in Summary
Thanks
Omar A.S