Oracle Primavera - PM6 Member for 19 years 2 months Member for 19 years 2 months Submitted by Chris Frank on Tue, 2007-03-13 06:05 Permalink RE: Critical Path in P5 Thanks Andrew Member for 20 years 11 months Member for 21 years Submitted by Andrew Podolny on Fri, 2007-03-09 09:48 Permalink RE: Critical Path in P5 Use Calculate Multiple Float paths under Schedule options -Advanced. Regards, Andrew Log in or register to post comments
Member for 19 years 2 months Member for 19 years 2 months Submitted by Chris Frank on Tue, 2007-03-13 06:05 Permalink RE: Critical Path in P5 Thanks Andrew
Member for 20 years 11 months Member for 21 years Submitted by Andrew Podolny on Fri, 2007-03-09 09:48 Permalink RE: Critical Path in P5 Use Calculate Multiple Float paths under Schedule options -Advanced. Regards, Andrew
Member for
19 years 2 monthsRE: Critical Path in P5
Thanks Andrew
Member for
20 years 11 monthsRE: Critical Path in P5
Use Calculate Multiple Float paths under Schedule options -Advanced.
Regards,
Andrew