Submitted by Dieter Wambach on Mon, 2007-03-05 12:14
actual units and level of efforts does work in P3e. There should be a mistake.
Some questions:
- LoE has no fixed duration, because its duration depends from other activities, so either fixed units or fixed untis/time - but this doesnt produce your situation.
- Did you create correct relationships (SS then FF)?
- Did a resource report actuals as well - via Timesheets?
Member for
21 years 10 monthsRE: Applying Progress to a Level of Effort Activity
Thanks guys.
Both of your contributions were helpfull in resolving my problem.
Member for
22 years 7 monthsRE: Applying Progress to a Level of Effort Activity
Check your Project Preferences under the Calculations tab. If you are entering Actual Units manually you need to make sure that the "Recalculate Actual Units and Costs when the duration % changes" is unchecked.
Member for
18 years 9 monthsRE: Applying Progress to a Level of Effort Activity
Phil,
actual units and level of efforts does work in P3e. There should be a mistake.
Some questions:
- LoE has no fixed duration, because its duration depends from other activities, so either fixed units or fixed untis/time - but this doesnt produce your situation.
- Did you create correct relationships (SS then FF)?
- Did a resource report actuals as well - via Timesheets?
Sorry, no answer, just more questions
Dieter