Applying Progress to a Level of Effort Activity

Member for

22 years 7 months

Check your Project Preferences under the Calculations tab. If you are entering Actual Units manually you need to make sure that the "Recalculate Actual Units and Costs when the duration % changes" is unchecked.

Member for

18 years 9 months

Phil,

actual units and level of efforts does work in P3e. There should be a mistake.

Some questions:

- LoE has no fixed duration, because its duration depends from other activities, so either fixed units or fixed untis/time - but this doesn’t produce your situation.

- Did you create correct relationships (SS then FF)?

- Did a resource report actuals as well - via Timesheets?



Sorry, no answer, just more questions



Dieter