You can create a shift calendar under - Enterprise>Resource Shifts - Create your two shifts in there and then attach it to your mechanical resource using the shift calendar button under units and prices. You should now be able to use the shifts up/down arrows to flick between shifts and set up your resource limits and profile.
Member for
18 years 8 monthsRE: Shutdown Plan - Help
You can create a shift calendar under - Enterprise>Resource Shifts - Create your two shifts in there and then attach it to your mechanical resource using the shift calendar button under units and prices. You should now be able to use the shifts up/down arrows to flick between shifts and set up your resource limits and profile.