Oracle Primavera - PM6 Member for 19 years Member for 19 years Submitted by Rama Krishnan on Sun, 2007-02-25 09:57 Permalink RE: How to sync Activity Dates & Resource dates Thanks Wasantha, It works Member for 22 years Member for 22 years 1 month Submitted by Wasantha Nanayakkara on Mon, 2007-02-19 05:36 Permalink RE: How to sync Activity Dates & Resource dates Rama Try to tick the drive activity dates in the resource tab.I think this will solve your problem. wasantha Log in or register to post comments
Member for 19 years Member for 19 years Submitted by Rama Krishnan on Sun, 2007-02-25 09:57 Permalink RE: How to sync Activity Dates & Resource dates Thanks Wasantha, It works
Member for 22 years Member for 22 years 1 month Submitted by Wasantha Nanayakkara on Mon, 2007-02-19 05:36 Permalink RE: How to sync Activity Dates & Resource dates Rama Try to tick the drive activity dates in the resource tab.I think this will solve your problem. wasantha
Member for
19 yearsRE: How to sync Activity Dates & Resource dates
Thanks
Wasantha, It works
Member for
22 yearsRE: How to sync Activity Dates & Resource dates
Rama
Try to tick the drive activity dates in the resource tab.I think this will solve your problem.
wasantha