Just a thought, is the project rescheduling after you make a change? There is a scheduling option called Schedule automatically when a change affects dates. This option is OK for small schedules but with 8000 activities I would have this switched off.
Member for
22 years 3 monthsRE: Primavera P3E/C version 5
Just a thought, is the project rescheduling after you make a change? There is a scheduling option called Schedule automatically when a change affects dates. This option is OK for small schedules but with 8000 activities I would have this switched off.
KB
Member for
22 years 8 monthsRE: Primavera P3E/C version 5
Kevin
Are you using a networked P3e??
Sometime the network traffic is the bottle neck of the slow respond issue.
Talk to your IT helpdesk (Standard reply will be we do not have any issue with our intranet ^&*)
HTH
Alex
Member for
23 years 11 monthsRE: Primavera P3E/C version 5
Check your PCs virtual memory and adjust to maximum