Primavera P3E/C version 5

Member for

22 years 3 months

Just a thought, is the project rescheduling after you make a change? There is a scheduling option called ’Schedule automatically when a change affects dates’. This option is OK for small schedules but with 8000 activities I would have this switched off.



KB

Member for

22 years 8 months

Kevin



Are you using a networked P3e??

Sometime the network traffic is the bottle neck of the slow respond issue.

Talk to your IT helpdesk (Standard reply will be we do not have any issue with our intranet ^&*)

HTH



Alex

Member for

23 years 11 months

Check your PC’s virtual memory and adjust to maximum