Critical Path

Member for

18 years 11 months

Hi Dave



The summary bar is a display of all of the activities within that band....how about rolling up critical activities so they are displayed on the summary bar?



1) Right click on the gantt chart and select Bars

2) From the list of bars select Critical Remaining

3) Click on the Bar Settings tab and confirm there’s a tick next to ’Show Bar When Collapsed’

4) When you collapse all of the bars - the summary bar will now display the critical red activities on top (Click on the Layout Options Bar and select Collapse All, Expand as appropriate)



Hope that helps



Sufian