Oracle Primavera - PM6 Member for 22 years 7 months Member for 22 years 8 months Submitted by Ronald Weaver on Wed, 2006-12-06 18:40 Permalink RE: Activity Codes Order This may sound odd but it works! After collapsing to a level, save the layout using the pull-down menu at the top left of you screen. This works in Project layouts also. But it doesn’t work for publish layouts. Good Luck Member for 22 years 8 months Member for 22 years 9 months Submitted by Alex Wong on Mon, 2006-12-04 23:01 Permalink RE: Activity Codes Order Hi everyone, I am back with some more problems; 1) Display the column and sort it but column be ware of the number remember add 000 in front 2) Yes display Resource Spreadsheet with no value in the spreadshee so the activity will have timescale @ the bottom 3) Cannot help you to click a few + and - Sign in a program 4) Assign one activity each for each calenda and print those activity out 5) If thats what you want I think it will be more appropriate to use a activity to representing the lag, that way you can copy and paste. HTH Alex Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Sun, 2006-12-03 02:25 Permalink RE: Activity Codes Order 1. Group the activity code under Project rather Global. 5. Use a dummy activity with that particular calander Log in or register to post comments
Member for 22 years 7 months Member for 22 years 8 months Submitted by Ronald Weaver on Wed, 2006-12-06 18:40 Permalink RE: Activity Codes Order This may sound odd but it works! After collapsing to a level, save the layout using the pull-down menu at the top left of you screen. This works in Project layouts also. But it doesn’t work for publish layouts. Good Luck
Member for 22 years 8 months Member for 22 years 9 months Submitted by Alex Wong on Mon, 2006-12-04 23:01 Permalink RE: Activity Codes Order Hi everyone, I am back with some more problems; 1) Display the column and sort it but column be ware of the number remember add 000 in front 2) Yes display Resource Spreadsheet with no value in the spreadshee so the activity will have timescale @ the bottom 3) Cannot help you to click a few + and - Sign in a program 4) Assign one activity each for each calenda and print those activity out 5) If thats what you want I think it will be more appropriate to use a activity to representing the lag, that way you can copy and paste. HTH Alex
Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Sun, 2006-12-03 02:25 Permalink RE: Activity Codes Order 1. Group the activity code under Project rather Global. 5. Use a dummy activity with that particular calander
Member for
22 years 7 monthsRE: Activity Codes Order
This may sound odd but it works!
After collapsing to a level, save the layout using the pull-down menu at the top left of you screen. This works in Project layouts also.
But it doesn’t work for publish layouts.
Good Luck
Member for
22 years 8 monthsRE: Activity Codes Order
Hi everyone,
I am back with some more problems;
1) Display the column and sort it but column be ware of the number remember add 000 in front
2) Yes display Resource Spreadsheet with no value in the spreadshee so the activity will have timescale @ the bottom
3) Cannot help you to click a few + and - Sign in a program
4) Assign one activity each for each calenda and print those activity out
5) If thats what you want I think it will be more appropriate to use a activity to representing the lag, that way you can copy and paste.
HTH
Alex
Member for
23 years 8 monthsRE: Activity Codes Order
1. Group the activity code under Project rather Global.
5. Use a dummy activity with that particular calander