Activity Codes Order

Member for

22 years 7 months

This may sound odd but it works!

After collapsing to a level, save the layout using the pull-down menu at the top left of you screen. This works in Project layouts also.

But it doesn’t work for publish layouts.

Good Luck

Member for

22 years 8 months

Hi everyone,



I am back with some more problems;



1) Display the column and sort it but column be ware of the number remember add 000 in front



2) Yes display Resource Spreadsheet with no value in the spreadshee so the activity will have timescale @ the bottom



3) Cannot help you to click a few + and - Sign in a program



4) Assign one activity each for each calenda and print those activity out



5) If thats what you want I think it will be more appropriate to use a activity to representing the lag, that way you can copy and paste.



HTH



Alex

Member for

23 years 8 months

1. Group the activity code under Project rather Global.



5. Use a dummy activity with that particular calander