Export P3e 5.0 to MS Project

Member for

19 years 8 months

Has any one experienced an error message when trying import from Project Pro 2003 that refers to the Call was the refused by the callee??? If u need more data let me know.



Many thanks

Member for

19 years

Due to client requests, I also have to export to MPP. I have found that programmes do not schedule as you would expect them to. There appear to be fixed dates applied to activities which upset the calculations. I have also had a problem with calendars, but can’t remember how I fixed it. I think I just set up the calendars manually.