Oracle Primavera - PM6 Member for 20 years 6 months Member for 20 years 6 months Submitted by Rashid Iqbal on Thu, 2006-10-12 12:09 Permalink RE: Unit and quantity Asif, I think your excavation is a BOQ item and you are to be paid against it. If this is the case then add your BOQ items as Material resources and put 100 cu.m in the BQ and 5 dollars in Rate/Unit. Hope it helps. Regards Rashid Log in or register to post comments
Member for 20 years 6 months Member for 20 years 6 months Submitted by Rashid Iqbal on Thu, 2006-10-12 12:09 Permalink RE: Unit and quantity Asif, I think your excavation is a BOQ item and you are to be paid against it. If this is the case then add your BOQ items as Material resources and put 100 cu.m in the BQ and 5 dollars in Rate/Unit. Hope it helps. Regards Rashid
Member for
20 years 6 monthsRE: Unit and quantity
Asif,
I think your excavation is a BOQ item and you are to be paid against it. If this is the case then add your BOQ items as Material resources and put 100 cu.m in the BQ and 5 dollars in Rate/Unit.
Hope it helps.
Regards
Rashid