Your point is valid however there are always exceptions. Splitting activity bars would help me with KPI analysis, therefore becoming quite usefull on a number of my projects. What Id say to Primaver is its always good to have options, make it possible and give us the choice to use it or not.
You can "split" using suspend/resume or an activity specific calander, but not under resource levelling.
Primavera has always resisted the temptation to allow multiple instances of the same activity number as in MSP. While this feature may help planning engineers, its a cost engineering nightmare. I am optimistic that Primavera will continue to resist imnplementing what I see as a mistake.
Member for
19 years 3 monthsRE: Is it possible to split activity bars?
David,
- I agree, we can "split" using suspend/resume but only for activities in progress, others we can not.
-Should using an activity specific calander,
Member for
19 years 2 monthsRE: Is it possible to split activity bars?
David,
Your point is valid however there are always exceptions. Splitting activity bars would help me with KPI analysis, therefore becoming quite usefull on a number of my projects. What Id say to Primaver is its always good to have options, make it possible and give us the choice to use it or not.
Kym.
Member for
21 yearsRE: Is it possible to split activity bars?
You can "split" using suspend/resume or an activity specific calander, but not under resource levelling.
Primavera has always resisted the temptation to allow multiple instances of the same activity number as in MSP. While this feature may help planning engineers, its a cost engineering nightmare. I am optimistic that Primavera will continue to resist imnplementing what I see as a mistake.