Oracle Primavera - PM6 Member for 19 years 7 months Member for 19 years 7 months Submitted by Karim Mounir on Sat, 2006-08-26 02:49 Permalink RE: Lose baseline when export file to P3 try this: restore the baseline which u are using in P5 first then export it to P3. after this export the updated schedule separately. Log in or register to post comments
Member for 19 years 7 months Member for 19 years 7 months Submitted by Karim Mounir on Sat, 2006-08-26 02:49 Permalink RE: Lose baseline when export file to P3 try this: restore the baseline which u are using in P5 first then export it to P3. after this export the updated schedule separately.
Member for
19 years 7 monthsRE: Lose baseline when export file to P3
try this:
restore the baseline which u are using in P5 first then export it to P3.