Dayanidhi, When you say you can modify the resource, do you mean I can delete the existing and replace with another? Because when I tried doing this by exporting the resources and resource assignments to excel and imported the same excel file after replacing a resource on one of the activity. But all it did was added the new resource but the previous one is still there. So again my question is can I relpace a resource by adding a new one and deleting the old using SDK?
Member for
19 years 2 months
Member for19 years2 months
Submitted by Luiz Eduardo on Sat, 2006-09-02 09:18
There is an EXCEL file(Activity4.xls)available from Primavera website; using SDK modules(VBA)you can talk with the Primavera resources, you can get the resources, and modify it and set the resources in P5 via the same Excel file. I hope this will save your time.
Member for
20 years 5 months
Member for20 years5 months
Submitted by Giannis Kostis on Tue, 2006-07-11 05:04
Member for
22 years 8 monthsRE: P5 Resource Assignment
Hi
You can use the importing function to update the resource. You do need to learn exactly how to do it.
I had a special tool that help me to do all that including update resource, project cod, create activities with loaded resource...
It is really useful if you dont want to know how to do SDK and VBA programming
Alex
Member for
19 years 4 monthsRE: P5 Resource Assignment
Dayanidhi, When you say you can modify the resource, do you mean I can delete the existing and replace with another? Because when I tried doing this by exporting the resources and resource assignments to excel and imported the same excel file after replacing a resource on one of the activity. But all it did was added the new resource but the previous one is still there. So again my question is can I relpace a resource by adding a new one and deleting the old using SDK?
Member for
19 years 2 monthsRE: P5 Resource Assignment
Where can i find this "Activity4.xls"?
Thanks
Luiz E.
Member for
22 years 7 monthsRE: P5 Resource Assignment
There is an EXCEL file(Activity4.xls)available from Primavera website; using SDK modules(VBA)you can talk with the Primavera resources, you can get the resources, and modify it and set the resources in P5 via the same Excel file. I hope this will save your time.
Member for
20 years 5 monthsRE: P5 Resource Assignment
Is it possible to export Budgeted units from P5 when the resource has been defined as material ?
Thanks
Member for
20 years 3 monthsRE: P5 Resource Assignment
Hello Gianis,
Im practising Pv5.0.
Im encoding the resource assignement, the old way, one by one.
regards,