Thanks Julie and David. I was able to get the required column in Resource Assignments window. Its a bit weird, the way this software works, but nontheless things are working out one way or the other, so I am a happy customer again, atleast for the time being.
You cannot do this in any Activity layout in P5, BUT you can do it in the resource asignment view. This is the equivalent of "Format Organise" by resource in P3 3,1.
Member for
20 years
Member for20 years
Submitted by Julie Scully on Mon, 2006-06-26 23:51
You need to add the column ‘budgeted labour units’ to your layout. There are 3 types of resources in P5 - labour, non-labour and materials. And unfortunately you need to use UDFs to get the total budgeted units in a column.
Member for
22 years 10 monthsRE: Budget Units Column
Thanks Julie and David. I was able to get the required column in Resource Assignments window. Its a bit weird, the way this software works, but nontheless things are working out one way or the other, so I am a happy customer again, atleast for the time being.
Cheers
Zafar
Member for
21 yearsRE: Budget Units Column
Zafar,
You cannot do this in any Activity layout in P5, BUT you can do it in the resource asignment view. This is the equivalent of "Format Organise" by resource in P3 3,1.
Member for
20 yearsRE: Budget Units Column
Zafar
You need to add the column ‘budgeted labour units’ to your layout. There are 3 types of resources in P5 - labour, non-labour and materials. And unfortunately you need to use UDFs to get the total budgeted units in a column.