Heres a thought.
Create two numeric custom data items. First is StdDur (Standard Duration), other is RainDur (Rainy Season Duration).
Use Global Change to load all the current OrigDur values into StdDur (so you dont lose them).
Then use Global Change again to load StdDur*1.3 into RainDur.
Now - backup the project so you dont mess it up.
Use Global Change to say IF ES is within the rainy season - then OrigDur=RainDur else OrigDur=StdDur. You can make more complex if the IF part to also check EF, etc (dependent upon your comfort with Global Change).
You can constantly re-run the Global Change on variations updates to your schedule. Youll want to make sure you have properly baselined your target so you dont lose what your original plan was.
Can also do something similar to adjust manhours or manpower (whichever you use for manpower reports) - have to make a similar set of custom data-items.
Hope that helps,
T
Member for
19 years 9 months
Member for19 years10 months
Submitted by Sergey Kiselev on Wed, 2006-06-21 16:28
a) Activities which must be executed only during summer time - Calendar with non-working period during winter.
b) Activities must start at summer and continues during winter - Add predecessor milestone and give to it Calendar from point A.
c) Activities with reduced production during winter period - Calendar with % decrease in working period. For example 30% decrease means that you have only 5,6 hours a day.
Member for
19 years 5 months
Member for19 years6 months
Submitted by Nigel Winkley on Wed, 2006-06-14 04:59
Not sure that you can use a "productivity factor" against either resources or activities. My initial suggestion would be to play around with the limits setting it to 30% and extending the durations to suit.
Someone else out there in cyberworld may know of a better solution. Previously, in a similar situation, I have just extended the durations accordingly. This was done manually and as things slipped had to be re-done as the activities moved into normal working. Have you tried using a resource calendar?
I am doing something similar to this, but instead of a rainy season we have winter work where the productivity lowers by 30%. Is there a way to show productivity on Primavera Version 5, or must I do the same thing, create a calendar with shorter days in the winter months (I would prefer not to do this).
Thanks,
Paula
Member for
20 years
Member for20 years
Submitted by Marcio Sampaio on Tue, 2006-06-13 08:52
Set up a rainy season calendar - using a holiday for the rainy season. All activities can then be scheduled with that calendar - including week-end/public holidays etc - and with the logic links, successors will follow.
Member for
19 years 1 monthRE: Rainy Season
Heres a thought.
Create two numeric custom data items. First is StdDur (Standard Duration), other is RainDur (Rainy Season Duration).
Use Global Change to load all the current OrigDur values into StdDur (so you dont lose them).
Then use Global Change again to load StdDur*1.3 into RainDur.
Now - backup the project so you dont mess it up.
Use Global Change to say IF ES is within the rainy season - then OrigDur=RainDur else OrigDur=StdDur. You can make more complex if the IF part to also check EF, etc (dependent upon your comfort with Global Change).
You can constantly re-run the Global Change on variations updates to your schedule. Youll want to make sure you have properly baselined your target so you dont lose what your original plan was.
Can also do something similar to adjust manhours or manpower (whichever you use for manpower reports) - have to make a similar set of custom data-items.
Hope that helps,
T
Member for
19 years 9 monthsRE: Rainy Season
a) Activities which must be executed only during summer time - Calendar with non-working period during winter.
b) Activities must start at summer and continues during winter - Add predecessor milestone and give to it Calendar from point A.
c) Activities with reduced production during winter period - Calendar with % decrease in working period. For example 30% decrease means that you have only 5,6 hours a day.
Member for
19 years 5 monthsRE: Rainy Season
Paula
Not sure that you can use a "productivity factor" against either resources or activities. My initial suggestion would be to play around with the limits setting it to 30% and extending the durations to suit.
Someone else out there in cyberworld may know of a better solution. Previously, in a similar situation, I have just extended the durations accordingly. This was done manually and as things slipped had to be re-done as the activities moved into normal working. Have you tried using a resource calendar?
Nige
Member for
19 years 5 monthsRE: Rainy Season
I am doing something similar to this, but instead of a rainy season we have winter work where the productivity lowers by 30%. Is there a way to show productivity on Primavera Version 5, or must I do the same thing, create a calendar with shorter days in the winter months (I would prefer not to do this).
Thanks,
Paula
Member for
20 yearsRE: Rainy Season
Thats it!! So eazy!!
Thanks and Reagards.
Member for
19 years 5 monthsRE: Rainy Season
Calendars!
Set up a rainy season calendar - using a holiday for the rainy season. All activities can then be scheduled with that calendar - including week-end/public holidays etc - and with the logic links, successors will follow.
Hope this helps.
Nige