58 views of yout post and no reply!! Couldnt resist the challenge. Need to know more about what dates you are actually looking at. If you group and sort by Project so that dates role up to the project level, what are Finish, Early Finish and Remaining early Finish, with or without "preserve"
Member for
21 yearsRE: Project Levelling
Paula,
58 views of yout post and no reply!! Couldnt resist the challenge. Need to know more about what dates you are actually looking at. If you group and sort by Project so that dates role up to the project level, what are Finish, Early Finish and Remaining early Finish, with or without "preserve"