Oracle Primavera - PM6 Member for 20 years 5 months Member for 20 years 5 months Submitted by Zubair Usmani on Fri, 2006-05-19 07:31 Permalink RE: obtain data from P5 to generate scurve/histogram Try to get from somebody an excel sheet(Containing Micro Programme to fetch the data directly from P5) or U can directly save a Report in Excel sheet by just changing the format of report in save as. Member for 20 years Member for 20 years Submitted by Marcio Sampaio on Thu, 2006-05-18 10:55 Permalink RE: obtain data from P5 to generate scurve/histogram Hi Onny; Go on assingments (icon on left). Create you lay-out with budgeted, actual, or anything u want. All units will be shown on timescale and u can copy / paste to Excel. Regards. Log in or register to post comments
Member for 20 years 5 months Member for 20 years 5 months Submitted by Zubair Usmani on Fri, 2006-05-19 07:31 Permalink RE: obtain data from P5 to generate scurve/histogram Try to get from somebody an excel sheet(Containing Micro Programme to fetch the data directly from P5) or U can directly save a Report in Excel sheet by just changing the format of report in save as.
Member for 20 years Member for 20 years Submitted by Marcio Sampaio on Thu, 2006-05-18 10:55 Permalink RE: obtain data from P5 to generate scurve/histogram Hi Onny; Go on assingments (icon on left). Create you lay-out with budgeted, actual, or anything u want. All units will be shown on timescale and u can copy / paste to Excel. Regards.
Member for
20 years 5 monthsRE: obtain data from P5 to generate scurve/histogram
Try to get from somebody an excel sheet(Containing Micro Programme to fetch the data directly from P5)
or
U can directly save a Report in Excel sheet by just changing the format of report in save as.
Member for
20 yearsRE: obtain data from P5 to generate scurve/histogram
Hi Onny;
Go on assingments (icon on left). Create you lay-out with budgeted, actual, or anything u want.
All units will be shown on timescale and u can copy / paste to Excel.
Regards.