Overall Physical %

Member for

20 years

Thanks Julie,



Now it is clear to me.



Regards.

Member for

20 years

Marcio



From the bulletin...



"At the summary level, the Performance % complete is calculated as follows:



Performance % Complete = (BCWP * 100) / BAC



(Where the BCWP is the Budgeted Cost of Work Performed and the BAC is the Budget At Completion)



BCWP is calculated as Activity % Complete * Baseline Total Cost"



Cheers

Julie


Member for

20 years

Heelo Julie,



Do u know why Costs assingned is a condition? Why not units only?



Regards.

Member for

20 years

Summarising the physical % complete is currently an enhancement request that Primavera are looking into. They have a workaround on the knowledgebase (bulletin # prim11292), but one of the conditions is having costs assigned to the activities.



HTH



Cheers

Julie