Summarising the physical % complete is currently an enhancement request that Primavera are looking into. They have a workaround on the knowledgebase (bulletin # prim11292), but one of the conditions is having costs assigned to the activities.
HTH
Cheers
Julie
Member for
20 years
Member for20 years
Submitted by Marcio Sampaio on Tue, 2006-05-09 10:08
Member for
20 yearsRE: Overall Physical %
Thanks Julie,
Now it is clear to me.
Regards.
Member for
20 yearsRE: Overall Physical %
Marcio
From the bulletin...
"At the summary level, the Performance % complete is calculated as follows:
Performance % Complete = (BCWP * 100) / BAC
(Where the BCWP is the Budgeted Cost of Work Performed and the BAC is the Budget At Completion)
BCWP is calculated as Activity % Complete * Baseline Total Cost"
Cheers
Julie
Member for
20 yearsRE: Overall Physical %
Heelo Julie,
Do u know why Costs assingned is a condition? Why not units only?
Regards.
Member for
20 yearsRE: Overall Physical %
Summarising the physical % complete is currently an enhancement request that Primavera are looking into. They have a workaround on the knowledgebase (bulletin # prim11292), but one of the conditions is having costs assigned to the activities.
HTH
Cheers
Julie
Member for
20 yearsRE: Overall Physical %
Hello Habbani;
Try to see what i wrote on BL Cost % Complete - Summary Roll-up here in Primavera Enterprise - Teamplay / P3e & P3ec category.
http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=21607
Hope it helps.
Regards.
Marcio Eduardo