I already did the Payments schedule and it is working. The most difficult thing is to do the links between the activities that generates payments events and the milestones.
I create a diferent project with the milestones - payment events - and integrate with the timeschedule. For the time being, its working.
Any opinion??
Regards.
Marcio Eduardo.
Rio de Janeiro - Brazil
Member for
20 years 2 months
Member for20 years2 months
Submitted by MUHAMMAD IQBAL on Tue, 2005-11-15 04:21
Member for
20 yearsRE: Payments schedule
Hi Muhammad,
The project file is too big (more than 7.000 activities - 20 MB).
Regards.
Marcio.
Member for
20 years 2 monthsRE: Payments schedule
HI
Marcio Sampaio
I was doing it by % wt Assinment .
so at the end of month wat so ever will be EV same will paided to contactor so very sipmle
can i have your project so that i can reveiw and comments
regards
Member for
20 yearsRE: Payments schedule
Thanks Muhammad,
I already did the Payments schedule and it is working. The most difficult thing is to do the links between the activities that generates payments events and the milestones.
I create a diferent project with the milestones - payment events - and integrate with the timeschedule. For the time being, its working.
Any opinion??
Regards.
Marcio Eduardo.
Rio de Janeiro - Brazil
Member for
20 years 2 monthsRE: Payments schedule
yes it is very nice idea from u
but you will be happy to hear that i have already worked on it.
in Saudia i was been practising
Details can be provided
have fun
iqbal