Oracle Primavera - PM6 Member for 20 years Member for 20 years Submitted by Marcio Sampaio on Fri, 2005-11-11 14:35 Permalink RE: Resource progress (v.5.0). Rajeev, The option is select. But resources are still not automatically progressing. Im afraid its something new on V.5 (or a bug). Better return to P3e v.4.1 Regards. Marcio Eduardo. Member for 20 years Member for 20 years Submitted by Marcio Sampaio on Thu, 2005-11-10 14:41 Permalink RE: Resource progress (v.5.0). Ok. Ill try it and return to u results. Regards. Marcio Eduardo Member for 23 years 8 months Member for 23 years 8 months Submitted by Rajeev Nelliyodan on Thu, 2005-11-10 07:42 Permalink RE: Resource progress (v.5.0). Try clicking on "Recalculate Actual Units and Cost when duration % complete changes" under calculation tab in Project view. Log in or register to post comments
Member for 20 years Member for 20 years Submitted by Marcio Sampaio on Fri, 2005-11-11 14:35 Permalink RE: Resource progress (v.5.0). Rajeev, The option is select. But resources are still not automatically progressing. Im afraid its something new on V.5 (or a bug). Better return to P3e v.4.1 Regards. Marcio Eduardo.
Member for 20 years Member for 20 years Submitted by Marcio Sampaio on Thu, 2005-11-10 14:41 Permalink RE: Resource progress (v.5.0). Ok. Ill try it and return to u results. Regards. Marcio Eduardo
Member for 23 years 8 months Member for 23 years 8 months Submitted by Rajeev Nelliyodan on Thu, 2005-11-10 07:42 Permalink RE: Resource progress (v.5.0). Try clicking on "Recalculate Actual Units and Cost when duration % complete changes" under calculation tab in Project view.
Member for
20 yearsRE: Resource progress (v.5.0).
Rajeev,
The option is select. But resources are still not automatically progressing.
Im afraid its something new on V.5 (or a bug). Better return to P3e v.4.1
Regards.
Marcio Eduardo.
Member for
20 yearsRE: Resource progress (v.5.0).
Ok.
Ill try it and return to u results.
Regards.
Marcio Eduardo
Member for
23 years 8 monthsRE: Resource progress (v.5.0).
Try clicking on "Recalculate Actual Units and Cost when duration % complete changes" under calculation tab in Project view.