Resource progress (v.5.0).

Member for

20 years

Rajeev,



The option is select. But resources are still not automatically progressing.



I’m afraid it’s something new on V.5 (or a bug). Better return to P3e v.4.1



Regards.



Marcio Eduardo.

Member for

20 years

Ok.



I’ll try it and return to u results.



Regards.



Marcio Eduardo

Member for

23 years 8 months

Try clicking on "Recalculate Actual Units and Cost when duration % complete changes" under calculation tab in Project view.