Marcio, there is one more thing to understand. That is Performance % Complete. Please try and understand. I have some tips. But I am experimenting. Let me share with you once I am sure. Thanks, Amar.
I too had same problem. When you change Activity % Complete, based % Completion type (Physical / Duration / Units), the appropriate % will be considered.
For eg, if an activity % Completion type is Physical when you enter Activity % Complete as 5%, Physical % = 5%,
But I am not able to understand how you have % Complete in Baseline.
Member for
20 yearsRE: Compare progress
Amar,
I understand that Bl activity % Complete is how much activity must have progressed - until the actual data-date - based on baseline.
If its correct, i can use it like a planned progress and compare with "Activity % Complete".
Tell me if u agree.
Regards.
Marcio Eduardo
Member for
20 years 2 monthsRE: Compare progress
Marcio, there is one more thing to understand. That is Performance % Complete. Please try and understand. I have some tips. But I am experimenting. Let me share with you once I am sure. Thanks, Amar.
Member for
20 years 2 monthsRE: Compare progress
Marcio,
I too had same problem. When you change Activity % Complete, based % Completion type (Physical / Duration / Units), the appropriate % will be considered.
For eg, if an activity % Completion type is Physical when you enter Activity % Complete as 5%, Physical % = 5%,
But I am not able to understand how you have % Complete in Baseline.
Regards, Amar.