Open both projects, the one you want to copy from and the one you want to paste to.
Organize bij WBS, select the activities, copy, and past within the WBS of the new project.
You can also paste in the same project, now you have the activities double, and change the WBS of the copied activities
Because P3e is full multiproject youve to difine the wbs for each activity. When you dont use WBS it puts all activities in the same project (whats a part of the WBS)
regards,
Henk
Member for
20 years 1 month
Member for20 years1 month
Submitted by Wilmore Makonese on Thu, 2005-12-01 22:17
Highlight the activities you want to copy go to tools fragnet, store fragnet put ID & title, then open other project go to fragnet, retrieve fragnet than select.
If you copy the activities in one project first, open both and organise it by EPS/WBS. Then you can select them and drop it into the project you wand to paste. Make sure you have rights to both projects.
HTH
Alex
Member for
20 years 3 months
Member for20 years3 months
Submitted by Shah Shams Alam on Mon, 2005-11-07 13:52
Select both the projects in Entrprise breakdown structure using controll key. Right click and open, Both the projects will open. Now u can copy and paste.
Member for
20 years
Member for20 years
Submitted by Marcio Sampaio on Mon, 2005-11-07 12:32
Member for
21 years 3 monthsRE: V5 : Copying Actvities of one project to other
Open both projects, the one you want to copy from and the one you want to paste to.
Organize bij WBS, select the activities, copy, and past within the WBS of the new project.
You can also paste in the same project, now you have the activities double, and change the WBS of the copied activities
Because P3e is full multiproject youve to difine the wbs for each activity. When you dont use WBS it puts all activities in the same project (whats a part of the WBS)
regards,
Henk
Member for
20 years 1 monthRE: V5 : Copying Actvities of one project to other
I would suggest exporting the project( or activities ) you want and then importing it/them in the project you want it/them to be.
Member for
20 yearsRE: V5 : Copying Actvities of one project to other
Dear all;
This forum is for P3e users. We have another forum for P3 users.
Using this one to discuss about P3 cause confusion.
Best regards.
Marcio Eduardo.
Member for
20 yearsRE: V5 : Copying Actvities of one project to other
What!!??
Member for
20 yearsRE: V5 : Copying Actvities of one project to other
Muhammad,
Highlight the activities you want to copy go to tools fragnet, store fragnet put ID & title, then open other project go to fragnet, retrieve fragnet than select.
kind regards,
Harold
infrastructure/tower projs.
Member for
22 years 8 monthsRE: V5 : Copying Actvities of one project to other
MUHAMMAD
It is P3e not P3 therefore there is no such thing as fragnet.
Cheers
Alex
Member for
20 years 2 monthsRE: V5 : Copying Actvities of one project to other
hi
guys
why not u using "fragnent"
Member for
20 years 2 monthsRE: V5 : Copying Actvities of one project to other
Alex, Thank you.
Thanks to all for participation.
Cheers, Amar.
Member for
22 years 8 monthsRE: V5 : Copying Actvities of one project to other
Thats right becasue the software need to know which Node (EPS) you want to paste the activity that why you either group by "EPS/WBS" or Just "WBS"
Alex
Member for
20 years 2 monthsRE: V5 : Copying Actvities of one project to other
Alex,
I have projects structured by activity codes not by WBS. When I open two projects and try to paste, it could not be done.
However, by default, WBS Level 1 is project itself. I grouped two projects by WBS for Level 1 and then tried. It worked out!
Member for
22 years 8 monthsRE: V5 : Copying Actvities of one project to other
Amar
If you copy the activities in one project first, open both and organise it by EPS/WBS. Then you can select them and drop it into the project you wand to paste. Make sure you have rights to both projects.
HTH
Alex
Member for
20 years 3 monthsRE: V5 : Copying Actvities of one project to other
Select both the projects in Entrprise breakdown structure using controll key. Right click and open, Both the projects will open. Now u can copy and paste.
Member for
20 yearsRE: V5 : Copying Actvities of one project to other
Open both projects. Than copy and paste.