The best way to distribute multiple effort on one activity is to make your activity type (Resource dependant) and create a special calendar to this resource. Then assign the calendar to the resource. Then assign him to the activity with the total units. By the way there is no way to get 2 figures after decimal but Edit _ User preferences.
The best solution for distributing variable effort on an activity is to multiple assign the resource, select a start and finish date for the resource and assign the number of days for the period.
e.g.
Resource 1 starts 1st jan finishes end jan 20 man days
resource i starts 1st feb finishes end Feb 15 man days
etc etc
It works OK for me
You can add the start and finish dates to the resource window, right click on one of the title fields at the top and select start and finish fields.
Member for
23 years
Member for23 years
Submitted by Steven Oliver on Thu, 2005-10-27 09:37
using the same resource multiple times: This I am aware and using for projects. But I thinking how to load as I explained earlier. I have created a user defined curve and almost matched the distribution required.
"Curve" is available for global change field
"Curve" is not availble in activity column. Do you have any idea?
Member for
23 years
Member for23 years
Submitted by Steven Oliver on Thu, 2005-10-27 09:21
Perhaps, you have misunderstood. You can use the same resource multiple times on an activity. Specify the duration and the lag (lead) from the start of an activity.
Member for
20 yearsRE: V5 : Resource Distribution
Thanks for your help
Member for
20 years 11 monthsRE: V5 : Resource Distribution
The best way to distribute multiple effort on one activity is to make your activity type (Resource dependant) and create a special calendar to this resource. Then assign the calendar to the resource. Then assign him to the activity with the total units. By the way there is no way to get 2 figures after decimal but Edit _ User preferences.
Member for
20 years 2 monthsRE: V5 : Resource Distribution
Ok, I got it from Edit, user preferences. Any other method?
Member for
20 years 2 monthsRE: V5 : Resource Distribution
One more challenge:
I have activity duration in "Days"
and
Estimated Resource Units in "Manhours"
I converted the manhours to Mandays.
Is there any way to have decimals for Mandays for resource units I mean 1.5mandays, 0.5 Mandays, 2.75Mandays etc.
Member for
23 years 11 monthsRE: V5 : Resource Distribution
Check project options, it has a check box for allowing or dis-allowing this feature.
Open your project
Go to Enterprise
select Projects
Select Resources, the tab is on the top left hand side.
Regards
Dave
Member for
20 yearsRE: V5 : Resource Distribution
Is this suppose to work in any version of P3E? I can not add multiple occurrences of the same resource.
Thanks,
Brent
Member for
23 years 11 monthsRE: V5 : Resource Distribution
The best solution for distributing variable effort on an activity is to multiple assign the resource, select a start and finish date for the resource and assign the number of days for the period.
e.g.
Resource 1 starts 1st jan finishes end jan 20 man days
resource i starts 1st feb finishes end Feb 15 man days
etc etc
It works OK for me
You can add the start and finish dates to the resource window, right click on one of the title fields at the top and select start and finish fields.
Member for
23 yearsRE: V5 : Resource Distribution
As I said, Resource Curves are associated with resources, not activities
Member for
20 years 2 monthsRE: V5 : Resource Distribution
Thanks Steven.
using the same resource multiple times: This I am aware and using for projects. But I thinking how to load as I explained earlier. I have created a user defined curve and almost matched the distribution required.
"Curve" is available for global change field
"Curve" is not availble in activity column. Do you have any idea?
Member for
23 yearsRE: V5 : Resource Distribution
________________________________________________________
Sorry Steven, With that I will not know what is my total resource requirement for a particular resource.
________________________________________________________
Perhaps, you have misunderstood. You can use the same resource multiple times on an activity. Specify the duration and the lag (lead) from the start of an activity.
_______________________________________________________
Steven, I could copy an exitsting res curve and modify according to the requirement.
Do you know, how to add resource curve to activity column? or how to use resource curve field in global change to assign resorce curve in faster way./
_________________________________________________________
Unless your activity exactly equates to that which you can generate using a resource curve then you will not achieve your desired result.
Resource curves are associated with resources, not activities.
Member for
20 years 2 monthsRE: V5 : Resource Distribution
Steven, I could copy an exitsting res curve and modify according to the requirement.
Do you know, how to add resource curve to activity column? or how to use resource curve field in global change to assign resorce curve in faster way./
Member for
20 years 2 monthsRE: V5 : Resource Distribution
Sorry Steven, With that I will not know what is my total resource requirement for a particular resource.
Member for
23 yearsRE: V5 : Resource Distribution
Use a new resource for each period, using lags