P3 e&c Stand Alone & Data Transfer

Member for

20 years 5 months

Oops



I did not see the referenc to e&c.



I can only advise towards P3.



BR

JMFrade

Member for

20 years 2 months

Hi Jose,



Thanks for your participation. I was using the same technique all the way from P3 Ver 2.0, 3.0 and 3.1.



Do you think it is possible in Ver 4.1 e&c ??



I have not understood sub project concept in e&c . can you please explain in detail?

Member for

20 years 5 months

Hello Hamar



The best solution is:



Creat the project structure in such way that the sub-projects are organized by project phase:



Ex: Main proj: PROJ01

Sub: -ENG1 (Engineering)

Sub:- PRCO (Procurement/Construction))



The idea is:

Each site opens just the subproject is entitled to work with, even though he can see the other activities and suffers impacts from others.



the update is simple: The site taking care about the subproject send a backup to the other. The restore of the backup immediately updates the global project (after rescheduling).



Best regards

JMFrade


Member for

23 years

From the P3e (not very helpful) help.



You can "check out" projects so that they can be worked on remotely. Once a project is checked out, it can no longer be modified until it has been checked in. In addition to checking in the project, you may replace the existing project with the remote copy of the project by using the Import wizard.


Member for

20 years 2 months

Steven,



With manual I could make them work. Thanks.



Is there any way to use filter for check in and check out.

Member for

20 years 2 months

Steven, I think you are suggesting for e&c installed on server. I have problem in sending projects to site and receiving the updated project from site. Do you advise, this is still possible with Check in / out for standa alone versions? Need little more details please.