Resource Peak

Member for

20 years 6 months

It is really a very important function and i used it in my efforts to level the reosurces manually. Anyways, as now i know it is not there, i ’ll try to find some other method. Thanks a lot.



Regards

Rashid

Member for

20 years 7 months

I’m afraid this one is still missing in P3e Rashid.



The best way to go about this is to call Primavera and add you name/company to an enhancement request. If more users are missing this functionality there is a distinct chance it will be incorporated in one of the next releases.



Cheers,



Niek.

Member for

23 years 8 months

P3e/c or P3e is only 50% powerful on reports and in handling resource & cost account.Even it has flaw on organzing resource & cost account if you have multiple assignment on one activity.



Getting back to peak,it does not have this option.The only available is average on spread sheet option.



this is the same for resource profile.The profile do not have any flexibilty in changing y axis.It does not show data values on top of resource profile also as in p3 graphics.