Ive spent many nights figuring out what Im missing. I thought that using the "Period Closeout" function, P3e will automatically record the actual resource usage.
In my opinion, this is really an important function in terms of monitoring resource loaded schedules.
Now I have a good reason to tell my PM to upgrade to the new realease :-).
Member for
24 years 9 monthsRE: Actual Resource Usage
Thanks Alex for the quick reply.
Ive spent many nights figuring out what Im missing. I thought that using the "Period Closeout" function, P3e will automatically record the actual resource usage.
In my opinion, this is really an important function in terms of monitoring resource loaded schedules.
Now I have a good reason to tell my PM to upgrade to the new realease :-).
Thank you again.
Member for
22 years 8 monthsRE: Actual Resource Usage
C A
Answer your question - in Version 4.1 P3e or ec or teamplay
They do not have the function of Save Period Performance
This is one of the most important function in order to print out the exact Labor Histogram + Earn Value Curves.
Forturnately , this long loss function is now available in Version 5.0 which just lanuched two weeks ago.
In order to save the period performance you need to apply the actuals then save PP just link P3
HTH
Cheers
Alex