Construction Schedule Samples

Member for

20 years 4 months

At present, I considered this an intellectual property and in my ongoing project, this is confidential information.



Maybe someday.



As a guide, you can start with Work Breakdown Structure of your hotel project. Then, work with activity code in organizing your activities.



You can also resource and cost load your project, if, required by the project team, otherwise, just do the basic planning (plain schedule).