Adding Steps

Member for

20 years 6 months

Bill,



Thanks a lot. I forgot to click on the "Activity pct based on activity steps. It is really very useful this step function.



Regards,

J.S. Daniel

Member for

20 years 10 months

J.S,



You need to check two settings.

1. On the Project screen, calculations tab make sure "Activity Pct based on activity steps" is checked.

2. For the activity, make sure % compl type is Physical. This is on the status tab of activity form.



This will compute PCT of activity based on step progress.



Regards,

Bill