Progress Spotlight

Member for

21 years

Thanks for all the help. Tried Apply Actuals, and seemed to work ok.



Andy

Member for

22 years 7 months

P3e/c version 5.0 will cover all major missing features like progress spotlight, suspend resume dates? etc.,.

bye the way is the new version released?.

Member for

20 years 10 months

As David mentions, "Progress Spotlight" functionality will be available in forthcoming version 5. However, most of the functionality to status activities automatically as if they are progressing as planned is available in your current version.



Take a look at the feature "Apply Actuals." For activities, you wish to have actuals (starts, finishes, units & costs) automatically applied, you need to check autocompute actuals for each activity and also for each resource.



Regards,

Bill

Member for

23 years 11 months

You can actualy use the curtain facility as a spotlight, it does not automatically filter out all activities in the curtain, you have to do this manualy.



go to:- view / attachments / curtain





Hope this helps





Regards



Dave



Typo’s corrected !!!!!