Oracle Primavera - PM6 Member for 23 years Member for 23 years Submitted by Steven Oliver on Mon, 2005-02-14 04:46 Permalink RE: To Generate Resource report....Plz Help Use the Activity Usage Spreadsheet in conjunction with the Report Wizard. Ther are options to use data from the current screen with timescaled info. All the data you require is selectable from the report wizard. HTH Log in or register to post comments
Member for 23 years Member for 23 years Submitted by Steven Oliver on Mon, 2005-02-14 04:46 Permalink RE: To Generate Resource report....Plz Help Use the Activity Usage Spreadsheet in conjunction with the Report Wizard. Ther are options to use data from the current screen with timescaled info. All the data you require is selectable from the report wizard. HTH
Member for
23 yearsRE: To Generate Resource report....Plz Help
Use the Activity Usage Spreadsheet in conjunction with the Report Wizard. Ther are options to use data from the current screen with timescaled info. All the data you require is selectable from the report wizard.