It is only applicable when the technique for activity % complete is enabled as "activity percent complete" in the earned value section of the wbs definitions.
Regards
Member for
23 years 8 months
Member for23 years8 months
Submitted by Dinesh Kumar D… on Mon, 2005-01-24 06:12
The performance % complete is the progress on the activity whatever defined as criteria for % complete for an activity.It gets rolled up on WBS level and gives you a picture on the WBS level if the projects are tracked based on physical percentage rather than duration or units.
Member for
20 years 10 monthsRE: Performance % complete
Hi Dinesh,
It is only applicable when the technique for activity % complete is enabled as "activity percent complete" in the earned value section of the wbs definitions.
Regards
Member for
23 years 8 monthsRE: Performance % complete
Hi Anwar,
Thank you for your reply.
I have one activity with physical percentage as 40% while performance % is 41.67.Why is the difference and how it is being calculated.
Thanks & regards
Dinesh
Member for
20 years 10 monthsRE: Performance % complete
The performance % complete is the progress on the activity whatever defined as criteria for % complete for an activity.It gets rolled up on WBS level and gives you a picture on the WBS level if the projects are tracked based on physical percentage rather than duration or units.