Performance % complete

Member for

20 years 10 months

Hi Dinesh,

It is only applicable when the technique for activity % complete is enabled as "activity percent complete" in the earned value section of the wbs definitions.



Regards

Member for

23 years 8 months

Hi Anwar,



Thank you for your reply.



I have one activity with physical percentage as 40% while performance % is 41.67.Why is the difference and how it is being calculated.



Thanks & regards



Dinesh

Member for

20 years 10 months

The performance % complete is the progress on the activity whatever defined as criteria for % complete for an activity.It gets rolled up on WBS level and gives you a picture on the WBS level if the projects are tracked based on physical percentage rather than duration or units.