You can create new base methodologies in Methodology Manager by exporting an existing project in P3e and then importing it into MM. When you import the project you are given a choice on whether to use Actuals or Planned values for the existing project.

This is actually quite neat because you have a chance to improve your methodologies after they have been used - continuous improvement.