P3 to P3ec 3.5.1 conversion - errors

Member for

22 years 8 months



Thanks Paul for your views and suggestion.



I found the differneces between p3 and p3ec like Original duration, remaining duration. so i changed those in p3ec. and somehow managed the -ve total float to -1 now.

I think, that remaining -1 total float is because of level of effort which was hammock in p3.



Anyway, thnaks a lot.



Dhananjay

Member for

24 years 7 months

I am unable to specifically tell you why your project is giving negative float but here are some things to think about.



All scheduling products calculate differently and importing a schedule is a data conversion not a project conversion and when I end up with the same answer after converting anything but a simple project especially one with progress I would consider myself very lucky.



To find the problem you should look at the start and finish dates and floats of the activities one at a time from the start until you find difference. At this point you may wish to check the calendars, lags and lag calendar. Primavera Enterprise has an option of 4 lag calendars, not just the predecessor as in P3. Check the autocost rules maybe the Remaining Duration has calculated differently or you may find a constraint has been handled differently. I have noticed that P3e handles Expected Finish Constraints differently to P3 when an Activity has progress, but I have not work through the issues to find out why.



Regards

Paul E Harris