Primavera Project Planner - P3 Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Tue, 2016-11-15 14:15 Permalink wrong forum go to project wrong forum go to project higlight your project go to the calculations tab under resource assignments make sure that subtract actual from at completion is checked NOT ADD actual to remaining Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Tue, 2016-11-15 14:15 Permalink wrong forum go to project wrong forum go to project higlight your project go to the calculations tab under resource assignments make sure that subtract actual from at completion is checked NOT ADD actual to remaining