Primavera Project Planner - P3 Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Fri, 2015-11-06 15:50 Permalink The only way to do it is to The only way to do it is to fool it and create a summary dummy activity that has the same total costs as the project total costs. You just have to know that it is there and not double dip it and make it a new WBS Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Fri, 2015-11-06 15:50 Permalink The only way to do it is to The only way to do it is to fool it and create a summary dummy activity that has the same total costs as the project total costs. You just have to know that it is there and not double dip it and make it a new WBS
Member for
16 years 3 monthsThe only way to do it is to
The only way to do it is to fool it and create a summary dummy activity that has the same total costs as the project total costs. You just have to know that it is there and not double dip it and make it a new WBS