It is a simple matter to move P3 schedules; just copy everything in the P3WIN\PROJECTS\ folder to the new PROJECTS folder. A P3 schedule consists of 11- 21 different files, all starting with the same 4-character project name. It does not matter which folder they are located in as long as all of the files remain together. Good luck!
Member for
22 years 10 monthsTerry, It is a simple matter
Terry,
It is a simple matter to move P3 schedules; just copy everything in the P3WIN\PROJECTS\ folder to the new PROJECTS folder. A P3 schedule consists of 11- 21 different files, all starting with the same 4-character project name. It does not matter which folder they are located in as long as all of the files remain together. Good luck!