Dear guys, i have a problem on p6, on how to change activity id's from numbers to words, inorder to create a header for my activities, and also, please do inform me on how to collapse and expand activities in p6.

Regards,

Ryan

Member for

22 years 9 months

Shima,

P3 does not allow to change the planninig unit (your "duration type") of a project

Click Tools, Project Utilities, Copy, select the project you want to change the planning unit

then give the NEW project another name or select another Windows folder

select the planning unit DAY for the new project, and click OK

P3 only changed the planning unit from HOUR to DAY, so you will now use a Global Change to change the values of the Original Duration field:

Click Tools, Global Change; then create a new global change where you will divide Original Duration by the number of hours per day in the project calendar

Hope this helps

Alexandre