Dear guys, i have a problem on p6, on how to change activity id's from numbers to words, inorder to create a header for my activities, and also, please do inform me on how to collapse and expand activities in p6.
Regards,
Ryan
Member for
22 years 9 months
Member for22 years9 months
Submitted by Alexandre Faul… on Mon, 2012-04-16 10:57
P3 does not allow to change the planninig unit (your "duration type") of a project
Click Tools, Project Utilities, Copy, select the project you want to change the planning unit
then give the NEW project another name or select another Windows folder
select the planning unit DAY for the new project, and click OK
P3 only changed the planning unit from HOUR to DAY, so you will now use a Global Change to change the values of the Original Duration field:
Click Tools, Global Change; then create a new global change where you will divide Original Duration by the number of hours per day in the project calendar
Member for
13 years 6 monthsDear guys, i have a problem
Dear guys, i have a problem on p6, on how to change activity id's from numbers to words, inorder to create a header for my activities, and also, please do inform me on how to collapse and expand activities in p6.
Regards,
Ryan
Member for
22 years 9 monthsShima,P3 does not allow to
Shima,
P3 does not allow to change the planninig unit (your "duration type") of a project
Click Tools, Project Utilities, Copy, select the project you want to change the planning unit
then give the NEW project another name or select another Windows folder
select the planning unit DAY for the new project, and click OK
P3 only changed the planning unit from HOUR to DAY, so you will now use a Global Change to change the values of the Original Duration field:
Click Tools, Global Change; then create a new global change where you will divide Original Duration by the number of hours per day in the project calendar
Hope this helps
Alexandre