P3 Progress Import - Actual Finish Dates

Member for

18 years 3 months

Try to re-export again to dbf, but with filter AF equals (blank) and Percent complete equals 100 to dbf

then put the date at AF column and import back to p3

this should work now

Member for

17 years 1 month

Please check if you have also updated the %complete. If it's still zero (0) then the dates will not really be actualized.

Member for

15 years 7 months

Ignore the commnt about Actual Finish dates Correctly importing prior to the December '08 data, these were alreadin input manually.