Primavera Project Planner - P3 Member for 16 years 8 months Member for 16 years 8 months Submitted by Ariel Malibiran on Tue, 2011-08-02 08:38 Permalink Thanks Mr. Winter... Thanks Mr. Winter... Member for 22 years 10 months Member for 22 years 10 months Submitted by Ronald Winter on Mon, 2011-08-01 15:15 Permalink Ariel, You need to put the Ariel, You need to put the new name of the schedule in the Project Group field and leave the Project Name field empty. Project Name is for when you have subprojects under the Project Group name. Good luck! Log in or register to post comments
Member for 16 years 8 months Member for 16 years 8 months Submitted by Ariel Malibiran on Tue, 2011-08-02 08:38 Permalink Thanks Mr. Winter... Thanks Mr. Winter...
Member for 22 years 10 months Member for 22 years 10 months Submitted by Ronald Winter on Mon, 2011-08-01 15:15 Permalink Ariel, You need to put the Ariel, You need to put the new name of the schedule in the Project Group field and leave the Project Name field empty. Project Name is for when you have subprojects under the Project Group name. Good luck!
Member for
16 years 8 monthsThanks Mr. Winter...
Thanks Mr. Winter...
Member for
22 years 10 monthsAriel, You need to put the
Ariel,
You need to put the new name of the schedule in the Project Group field and leave the Project Name field empty. Project Name is for when you have subprojects under the Project Group name. Good luck!