Primavera Project Planner - P3 Member for 21 years 8 months Member for 21 years 8 months Submitted by Rafael Davila on Thu, 2011-08-04 18:24 Permalink Before DD Early and Late S Before DD Early and Late S curves are equal to actual as Early Dates and Late Dates are set equal to to Actual Dates. After DD they are different unless all remaining work contributing to the S values are critical. Plan = Remaining Work after DD Log in or register to post comments
Member for 21 years 8 months Member for 21 years 8 months Submitted by Rafael Davila on Thu, 2011-08-04 18:24 Permalink Before DD Early and Late S Before DD Early and Late S curves are equal to actual as Early Dates and Late Dates are set equal to to Actual Dates. After DD they are different unless all remaining work contributing to the S values are critical. Plan = Remaining Work after DD
Member for
21 years 8 monthsBefore DD Early and Late S
Before DD Early and Late S curves are equal to actual as Early Dates and Late Dates are set equal to to Actual Dates. After DD they are different unless all remaining work contributing to the S values are critical.
Plan = Remaining Work after DD