Week schedule ?

Member for

14 years 10 months

Hi

Try using this specifications in your filter: 

 

Level 1

Early Start    LT    (Data Date + 7 days)

Actual Start  LT    (Data Date + 7 days)

Level 2

Percent Complete    NE    100%

 

Any questions let me know

Regards

Member for

15 years

Thanks for your reply harzelli, I know i must used filter but the problem is what's the right function must use to get right answer 

Member for

17 years

Hi

simply use spotlight (it's easy), and when print only the requested period.

if u want to show only the activities related to this period use a filter.

Regards